Data Centers · Investment Criteria

What Makes a Data Center Project Investable?

Institutional capital for data centers is abundant. The constraint is projects that meet the criteria. Eight factors separate the projects that close from the ones that stall — and most of them are within the developer's control.

The paradox of the current data center market: capital is genuinely abundant — pension funds, infrastructure PE, sovereign wealth, and debt funds all have active data center mandates — yet the majority of development projects struggle to close their capital stacks. The bottleneck is not investor appetite. It is the quality and completeness of the projects seeking investment.

Understanding what institutional investors and lenders actually require — not what developers hope they'll overlook — is the foundation of an investable project.

1. Secured Power

This is the single most important factor, and it is binary: either you have a credible path to power, or you don't. In the current market, "credible path" means one of three things: a signed grid interconnection agreement with a defined timeline, a behind-the-meter generation solution with a credible development plan, or a Power Purchase Agreement (PPA) with a generator that has construction-ready capacity.

LOIs, preliminary discussions with the utility, and "conversations with grid operators" do not constitute secured power. Investors and lenders have been caught by optimistic power narratives before. They are now significantly more rigorous in diligencing power specifically, often retaining independent power consultants to validate the path to energisation.

2. A Creditworthy Anchor Tenant

A signed lease from a hyperscaler or Tier-1 co-location customer is the instrument that unlocks the broadest and cheapest capital. Investment-grade or near-investment-grade tenant credit — Google, Microsoft, Amazon, Meta, Oracle — allows senior construction lenders to underwrite against contracted cash flows rather than speculative demand. The lease term matters: 10 years is the minimum for most institutional lenders; 15–20 years enables the most favourable financing terms.

Projects without anchor leases are fundable — but only at higher cost and with a more limited lender pool. Speculative development (building ahead of tenant commitments) requires a greater equity cushion and commands a higher cost of capital from debt providers willing to accept market risk.

3. A Proven Development Team

Investors back people. A development team that has delivered a comparable facility — same asset type, similar scale, similar complexity — carries significantly lower execution risk in an investor's assessment. The most important CV item for a data center developer is not the projects they've started. It is the projects they've delivered on time and on budget.

"Anyone can plan a data center. The investors who've been in this market for a decade are funding teams that can deliver one."

4. A Fixed-Price or GMP Construction Contract

Cost overruns are among the most frequent causes of equity impairment in data center development. A fixed-price Engineering, Procurement, and Construction (EPC) contract, or a Guaranteed Maximum Price (GMP) contract from a credible tier-1 contractor, transfers construction cost risk from the developer to the contractor. Lenders will not accept open-book construction cost estimates for senior debt. They require a fixed-price contract with a contractor of sufficient financial standing to back their guarantee.

5. Market Location with Structural Demand

Not all markets are equal. The most investable data center markets combine: proximity to major metropolitan areas (reducing network latency), power availability and cost (ideally sub-$50/MWh long-term), fibre infrastructure, a skilled construction workforce, and a permitting environment that is predictable and not prohibitively slow. Top-tier markets in North America include Northern Virginia (NOVA), Chicago, Dallas, Phoenix, and Silicon Valley. In Europe: Frankfurt, Amsterdam, London, Dublin, and — increasingly — Scandinavia for power availability and renewable energy.

6. ESG-Aligned Power Strategy

Institutional investors — particularly pension funds, sovereign wealth, and ESG-mandated infrastructure funds — are increasingly requiring data center portfolios to demonstrate a credible path to carbon neutrality. This affects site selection (markets with high renewable energy penetration), power procurement (renewable PPAs, RECs), cooling technology (lower-PUE liquid cooling), and waste heat recovery. Projects that cannot demonstrate an ESG-aligned power strategy face exclusion from a growing proportion of institutional mandates.

7. Appropriate Capital Structure

A data center project with 20% equity and 80% senior debt at a 50-basis-point premium to market is not well-structured — it is overleveraged and fragile to construction delays or cost overruns. Investable projects have capital structures that reflect actual risk: sufficient equity cushion to absorb reasonable downside scenarios, construction contingency of 10–15%, and debt terms that allow the project to service debt comfortably under base-case projections.

8. A Clear Exit or Hold Strategy

Equity investors need to see how they realise their return. The primary exit paths for data center equity: sale to a core infrastructure fund or REIT on stabilisation (the most common), IPO of the portfolio entity, or long-term hold with dividend recapitalisation. The most fundable projects are those where the exit path is credible and the anticipated stabilised value — based on comparable transactions — supports the equity return target.

What Separates Funded from Unfunded

Most projects that fail to close capital are weak on one or two of these criteria — and the weakness is typically known to the developer before the capital raise begins. The more productive approach: identify the gaps early, fix what can be fixed, and present honestly on what remains uncertain. Investors who are presented with a clear-eyed assessment of risks — alongside a credible mitigation plan — consistently respond better than those presented with a flawless narrative that unravels in due diligence.

Frequently Asked Questions
Institutional investors prioritise: secured power (grid connection agreement or behind-the-meter generation), a creditworthy anchor tenant (ideally a hyperscaler on a long-term lease), proven development team, fixed-price construction contract, prime market location, ESG-aligned power strategy, appropriate capital structure, and a credible exit or hold path.
For senior construction debt at institutional rates, a signed lease with a creditworthy tenant is generally required. Without one, developers rely on higher-cost equity-heavy structures. Some debt providers will lend against speculative development with strong developer track record and market fundamentals, but at higher rates and lower leverage.
A Guaranteed Maximum Price (GMP) contract caps the total construction cost — the contractor bears any costs above the GMP. It is distinct from a lump-sum fixed-price EPC contract in that it may allow cost savings to be shared between developer and contractor. Both structures transfer cost risk from developer to contractor and are required by most institutional construction lenders.
In North America: Northern Virginia, Chicago, Dallas, Phoenix, and Silicon Valley. In Europe: Frankfurt, Amsterdam, London, Dublin, and Scandinavia. Selection criteria: power availability and cost, metropolitan proximity, fibre infrastructure, permitting predictability, and workforce availability. Northern Virginia alone hosts approximately 70% of the world's internet traffic routing.
Institutional investors increasingly require: credible path to carbon neutrality (timeline and mechanism), renewable energy procurement strategy (PPAs, RECs, or on-site generation), low-PUE cooling technology, water usage efficiency, and waste heat recovery plans where practical. Projects without ESG strategies face exclusion from a growing share of institutional mandates.
Most institutional lenders require 30–40% equity (or equity-equivalent) in the capital structure, ensuring sufficient cushion to absorb construction cost overruns and delays without impairing debt service. Construction contingency of 10–15% of total project cost is standard. Overleveraged structures — below 20% equity — face lender rejection and expose equity investors to impairment on relatively modest downside scenarios.
Stabilised data centers are valued on a cap rate (income capitalisation) basis — stabilised NOI divided by market cap rate. Cap rates for hyperscale assets with long-term investment-grade leases currently range from 5–7% in primary markets. At a 6% cap rate, a facility generating $60M of stabilised NOI is valued at $1B. Development profit is the difference between this value and total build cost.
A Power Purchase Agreement (PPA) is a long-term contract to purchase electricity from a specific generator — typically a renewable energy project — at a fixed or formula price. Data center operators use PPAs to secure power supply, manage energy cost volatility, and demonstrate renewable energy procurement for ESG purposes. PPAs do not eliminate grid interconnection requirements but can satisfy ESG mandates and provide cost certainty.

Finance Your Data Center Project

OAKRG advises on data center project finance, construction debt, hyperscale equity raises, and energy-linked infrastructure capital across North America, Europe, and Asia-Pacific.

Speak with an Advisor